
|
 |
Law Talk - PUBLIC WORKS AND THE IMPORTANCE OF THE PAYMENT BOND
By Sam K. Abdulaziz
Attorney at Law
In a public works contract, what happens if
the County failed to obtain a payment bond from the now bankrupt general
contractor who has not paid his subcontractor? Does the subcontractor get paid?
By whom? A recent case that was decided by the California Court of Appeal
addressed this very question.
In 1998, N.V. Heathorn, Inc. (“HEATHORN”) entered into a contract with Nielsen
Dillingham Builders, Inc. (“NDBI”). NDBI was “acting in the capacity of a
general contractor on a public works project” — namely improvement work on the
San Mateo County Health Center. HEATHORN was the subcontractor providing labor
and materials for this project. By mid 2001, NDBI owed HEATHORN over $400,000
for HEATHORN’s contributions to the project. Therefore, HEATHORN filed a lawsuit
against NDBI. In turn, NDBI filed for bankruptcy, which relieved them of their
obligation to pay.
Under Civil Code section 3247, the public entity must require the original
contractor to file a payment bond if the project is for more than $25,000. The
County of San Mateo (“COUNTY”) did not do so in this case. Therefore, HEATHORN
was now left without a payment source.
In February 2003, HEATHORN submitted a claim to the COUNTY seeking damages it
should have been able to recover from NDBI. The COUNTY rejected this claim
making the following arguments: First, HEATHORN has not demonstrated an “injury”
under the Government Tort Claims Act; and second, the action was time-barred.
The Government Tort Claims Act allows someone to recover against a public entity
for injuries suffered only if the injury is of a nature that would be actionable
if caused by a private individual. That is to say, the court cannot hold the
government liable for causing harm to this subcontractor, if a regular person,
in the government’s shoes, would not be held liable. Moreover, the injury must
be caused by the COUNTY’s failure to exercise a duty—here, the duty to require a
payment bond. In response, if the public entity can show that “it exercised
reasonable diligence to discharge the duty,” the public entity will not be
liable. The trial court agreed with the COUNTY’s first argument and found in
favor of the COUNTY.
We have previously written about the importance of mechanic’s lien rights and
their constitutional authority. However, government projects are not subject to
mechanic’s liens because of sovereign immunity. Sovereign immunity is the
doctrine that bars an action against the government without its consent. The
only remedies available on public works are stop notices and actions on the
payment bond. Thus, the payment bond is essentially the equivalent of a
mechanic’s lien where the stop notice is inadequate due to insufficient funds.
As Heathorn emphasizes, ‘the lien rights of those who provide labor and
materials is protected through constitutional mandate in both the public and
private spheres.’ Our state Constitution guarantees that “laborers of every
class shall have a lien upon the property upon which they have bestowed labor or
furnished material for the value of such labor done and material furnished; and
the Legislature shall provide, by law, for the speedy and efficient enforcement
of such liens.’
With these considerations in mind, the Court of Appeal disagreed with the trial
court and found in favor of HEATHORN, the subcontractor. The Court found the
harm caused by the COUNTY’s failure to obtain a payment bond from NDBI and
neglecting its statutory duty, “qualifies as an ‘injury’ to support a cause of
action.”
Return to Year 2006
Topics
The information and comments throughout this website are intended to be of a general nature. Our comments/advice should not be relied upon without your seeking the aid and advice of legal counsel who will have the opportunity to take the time to research all your issues.
Abdulaziz, Grossbart & Rudman provides this information as a service to its friends &
clients. It is of a general nature and should not be used as a substitute for
specific legal advice. Any and all information set forth on our website relates
solely to California law. The information is not relevant and not applicable in
any other state or jurisdiction.
The firm can be reached at:
Abdulaziz, Grossbart & Rudman
P.O. Box 15458
North Hollywood, CA 91615-5458
(818) 760-2000
Facsimile (818) 760-3908 or by E-Mail at
Info@AGRLaw.net
Please note that any information you provide to
us via e-mail may be viewed by others and therefore, it is not a privileged
communication.
Copyright © 2006 by Abdulaziz, Grossbart & Rudman. All rights reserved.
|
 |