
|
 |
Law Talk - Should I Walk? Should I terminate?
By Sam K. Abdulaziz
Attorney at Law
Quite often we are asked whether a prime contractor should
terminate a subcontractor, or whether a subcontractor should walk from a
construction contract as a result of a disagreement over payment, work, changes
or otherwise. The answer to this is not simple. The results of "walking" or
"terminating" can be very severe since either one can be interpreted as a breach
of contract. The answer will always be factually driven and may not be something
that one can predict beforehand.
A breach of contract is when someone does something that he or she should not
have done or doesn't do something that he or she should have done. There are two
types of breaches. One is a major breach and the other is a minor breach. A
major breach is one that would keep the person who breached the contract from
attempting to recover anything. A minor breach is one where the person who
breached the contract may still be able to collect but the amount he or she
collects might be reduced by the damages resulting from that person's minor
breach.
Let us assume that the subcontractor walks, because the sub believes that the
prime contractor required a "change" and then would not pay the sub for the
"change". The prime feels the "change" was not truly a change in scope and
therefore nothing extra was due to the subcontractor. If it turns out that the
prime was right or the breach by the prime was minor, the subcontractor may then
be in major breach by walking. This means that the sub will not even be able to
collect the money due him and may subject himself to damages.
Our office has run into something that can help in making this determination.
However, it is not foolproof. It is called a "Request for Further Assurances,"
and is found in the Uniform Commercial Code that was adopted by California. If
you are lead to believe in good faith that the other side is not going to
perform its obligations, then you can request further assurances of the other
side's performance.
Section 251 of the Restatement of the Law, Contracts, Second Edition, states the
rule as follows:
(1)"Where reasonable grounds arise to believe that the obligor will commit a
breach by non-performance that would of itself give the obligee a claim for the
damages for total breach . . . the obligee may demand adequate assurance of due
performance and may, if reasonable suspend any performance for which he has not
already received the agreed exchange until he receives such assurance.
(2)The obligee may treat as a repudiation the obligor's failure to provide
within a reasonable time such assurance of due performance as is adequate in the
circumstances of the particular case."
This concept has been acknowledged in California's adoption of the Uniform
Commercial Code, Article 2, Sales. (See Cal. Uniform Commercial Code §2609.
Although the Uniform Commercial Code generally applies only to the sale of
goods, there is some authority that you might be able to use this procedure in
construction matters. The concept is similar to the established rule regarding
anticipatory breach. This is where someone refuses to perform even before their
obligation has arisen.
When you ask for further assurances and if you don't get those further
assurances, you may be able to treat the fact that you didn't get the further
assurances as a breach. Although this may still require you to determine if the
breach was major or minor, at least it gives you a way to determine the fact
that there was a breach.
It appears that the maxim that contractors are gamblers is true in this case as
well. There is nothing sure in the construction business.
Return to Year 2006
Topics
The information and comments throughout this website are intended to be of a general nature. Our comments/advice should not be relied upon without your seeking the aid and advice of legal counsel who will have the opportunity to take the time to research all your issues.
Abdulaziz, Grossbart & Rudman provides this information as a service to its friends &
clients. It is of a general nature and should not be used as a substitute for
specific legal advice. Any and all information set forth on our website relates
solely to California law. The information is not relevant and not applicable in
any other state or jurisdiction.
The firm can be reached at:
Abdulaziz, Grossbart & Rudman
P.O. Box 15458
North Hollywood, CA 91615-5458
(818) 760-2000
Facsimile (818) 760-3908 or by E-Mail at
Info@AGRLaw.net
Please note that any information you provide to
us via e-mail may be viewed by others and therefore, it is not a privileged
communication.
Copyright © 2006 by Abdulaziz, Grossbart & Rudman. All rights reserved.
|
 |