
|
 |
Law Talk - HOW TO USE THE CALIFORNIA
PRELIMINARY NOTICE TO COLLECT ON PAYMENT BONDS
By Sam K. Abdulaziz
Attorney at Law
By this time, anyone who is in the construction business is aware
that the "Pay if Paid" clause has been held to be unenforceable. This is a win
for subcontractors and material suppliers. Our office was involved in the
California Supreme Court case that rendered this decision.
Another recent case also helped subcontractors. This case had to do with public
works projects and the fact that sureties on public works projects would be held
responsible to pay a penalty imposed by the Public Contract Code. Although the
factual and procedural background of this case deals with public works, it is
possible that the same body of law can be used in the private works arena.
Several years ago our legislature enacted a body of law which has become known
as "Prompt Pay" legislation. Our office worked on and supported the legislation.
Essentially these statutes state that contractors, upon receipt of money from
owners, have a time certain in which to pay their subcontractors. The failure to
pay within the prescribed time can subject the contractor to a two percent (2%)
per month penalty and the recovery of attorney fees and cost, should one party
be required to sue the other party to collect the money owed.
The two percent (2%) penalty is two percent (2%) of the amount due per month for
each month that payment is not made. As you can see, the penalty could be quite
large.
The question recently answered by our Appellate Court was whether a surety who
issued a payment bond would be held responsible for the two percent (2%) penalty
when the bonded contractor fails to make the payment called for in the "Prompt
Pay" statutes. The answer was a resounding "yes."
Green Coast, a general contractor, entered into a contract with Caltrans for
work to be performed on Highway 150. Green Coast then entered into a subcontract
with Backlund whereby Backlund was to perform clearing, grubbing, excavation and
grading services for the sum of $269,650.00. Through the course of the work of
improvement, the contract between Green Coast and Backlund was increased to the
sum of $953,641.04. Although Green Coast had received payments from Caltrans,
Green Coast failed to pay its subcontractor Backlund. Backlund filed a Stop
Notice. Green Coast then misrepresented to Backlund that Caltrans had not paid
Green Coast for any of Backlund's work and further was contesting Backlund's
claim for such work. Green Coast then negotiated with Backlund telling Backlund
that if they would accept a lesser sum of money, Backlund would get paid
immediately by Green Coast in exchange for a release of the Stop Notice.
Backlund agreed to this, but Green Coast defaulted on this agreement and
Backlund subsequently discovered the deception. Backlund filed a lawsuit seeking
to recover on its contract and further sought to recover the two percent (2%)
interest penalty for failure to make timely payment. By the time Backlund filed
its complaint, Green Coast had filed for bankruptcy. The complaint was filed by
Backlund and against Washington International Insurance Company ("Washington"),
the surety who issued the payment and performance bond.
Washington filed a motion to strike the portion of the complaint that sought the
two percent (2%) interest penalty. Washington contended that under its bond, it
was only required to pay Backlund for the labor and materials used or consumed
on the work of improvement and not for the two percent (2%) penalty per month.
It further claimed that this two percent (2%) penalty did not represent an
out-of-pocket expense or an actual outlay of money.
The Appellate Court said that while no case law exists as to the meaning of the
word "claims" in this scenario, the fact is that claims include all amounts owed
to an unpaid subcontractor, which would include not only money owed for the
value of work put in place, but for the penalty imposed by the law. The Court
cited Civil Code Section 3226 which states in relevant part that any bond issued
will be construed most strongly against the surety in favor of all persons for
whose benefit such bond is given. Here, the bond was given for the benefit of
Backlund and therefore the bond should be construed most favorably to Backlund.
The Court held that claim for recovery of the two percent (2%) per month penalty
is a valid claim. What happened at the actual trial is unknown. It is important
to keep in mind that in order to be able to recover this two percent (2%)
penalty, the subcontractor must be able to prove that the actions of the
contractor violated California's "Prompt Pay" laws.
Return to Year 2006
Topics
The information and comments throughout this website are intended to be of a general nature. Our comments/advice should not be relied upon without your seeking the aid and advice of legal counsel who will have the opportunity to take the time to research all your issues.
Abdulaziz, Grossbart & Rudman provides this information as a service to its friends &
clients. It is of a general nature and should not be used as a substitute for
specific legal advice. Any and all information set forth on our website relates
solely to California law. The information is not relevant and not applicable in
any other state or jurisdiction.
The firm can be reached at:
Abdulaziz, Grossbart & Rudman
P.O. Box 15458
North Hollywood, CA 91615-5458
(818) 760-2000
Facsimile (818) 760-3908 or by E-Mail at
Info@AGRLaw.net
Please note that any information you provide to
us via e-mail may be viewed by others and therefore, it is not a privileged
communication.
Copyright © 2006 by Abdulaziz, Grossbart & Rudman. All rights reserved.
|
 |