
|
 |
Law Talk - THE COURT WILL NOT ALLOW THE CONTRACTOR TO CONTRADICT ITS
PREVIOUS COMPLAINT
By Sam K. Abdulaziz
Attorney at Law
Let me start by saying that I think this case is more of a
pleading case than a construction case. It does not say or clarify anything
about construction law or the licensing laws that we have not known before. It
merely clarifies the procedure of pleadings and what one can and cannot plead at
the appellate level.
This recent case stemmed from a contract entered into between an unlicensed
design contractor and an individual. Banis Restaurant Design Inc. (hereinafter “Banis”)
sued Borgata Serrano and Bank of America (hereinafter collectively referred to
as “Serrano”) claiming Serrano owed it an unpaid amount on the contract. The
trial court agreed with Serrano and denied Banis relief because Banis was not a
licensed contractor. Business and Professions Code section 7031 bars an
unlicensed contractor from "collection of compensation for the performance of
any act or contract where a license is required…” On appeal, Banis tried to
bring in facts to show that the absolute bar of section 7031 did not apply. The
court did not allow this.
A small legal lesson is in order. At the trial level, Serrano had filed a
demurrer that was upheld by the court. A demurrer is a response to the complaint
stating that even on those facts, there is no cause of action. This throws the
case out of court. The trial court in this case, upheld the demurrer. The issue
was whether an amendment would cure the defect and thus state a cause of action.
In July 2004, Banis filed a complaint to recover the unpaid balance on the
contract, alleging seven causes of action. The first cause was a breach of
contract action claiming that Banis entered into a contract with Serrano. Under
the December 2001 contract, Banis was “to provide design labor, materials,
equipment and services to be used and incorporated into the work of
improvement.” Thereafter, they entered into a series of additional agreements.
Banis alleged that the agreed sum to be paid was over $1.7 million of which they
have been paid approximately $1.5 million. The second cause of action was to
foreclose on a $200,000 mechanic’s lien filed against the property. The third
through sixth causes of action alleged alternative theories for recovery of the
unpaid balance. The seventh cause of action asserted that Banis had served a
stop notice on Serrano and although there were funds to pay the claims, Serrano
did not pay. Serrano filed a demurrer stating that Banis was not a licensed
contractor and was therefore barred from seeking relief for amounts owed under
the contract. In response, Banis stated that since the contract was for design
work, no contractor’s license was required. However, by its own pleading, the
contract was for far more than merely design work. The trial court did not allow
Banis to amend its pleading. The case was then brought before the appellate
court.
The appellate court agreed that Banis was a “contractor” within the meaning of
section 7026, since the complaint and the contract described work such as
drawings for electrical and plumbing plans as well as coordination of architects
and engineers. Significantly, the complaint in the first cause of action alleged
that the more than $1.7 million of labor, services, equipment, and materials
provided by the contractor were “used or consumed in” the project. Thus, Banis
Restaurant Design, Inc. is classified as a contractor and not merely a material
supplier. Since the contractor was not licensed, section 7031 barred the suit
for compensation on the unpaid balance on the contract.
As to whether Banis could amend its pleading, the court reiterated that it would
consider amendments that would cure the defect in the complaint that made it
demurrable. However, Banis could not avoid the defects of its original complaint
by filing an amended complaint that leaves out or directly contradicts facts
alleged earlier.
The court said that such an amendment would directly contradict its earlier
complaint. The court gave the following reasons: First, a mechanic’s lien can
only be filed when materials are physically incorporated into the structure
therefore characterizing them as fixtures. By filing a mechanic’s lien, Banis
admitted that the materials are fixtures on the property. Second, Banis’s
services were more than incidental labor. The contract described work such as
drawings for electrical and plumbing plans as well as coordination of architects
and engineers. With these reasons, the court found that the exemption under
section 7045 does not apply.
Although this case involved construction, and contractor related laws, the
outcome of the case turned mainly on procedure. However, the case does lead to
the fact that you should consult a competent attorney in your field should a
dispute arise.
Return to Year 2006
Topics
The information and comments throughout this website are intended to be of a general nature. Our comments/advice should not be relied upon without your seeking the aid and advice of legal counsel who will have the opportunity to take the time to research all your issues.
Abdulaziz, Grossbart & Rudman provides this information as a service to its friends &
clients. It is of a general nature and should not be used as a substitute for
specific legal advice. Any and all information set forth on our website relates
solely to California law. The information is not relevant and not applicable in
any other state or jurisdiction.
The firm can be reached at:
Abdulaziz, Grossbart & Rudman
P.O. Box 15458
North Hollywood, CA 91615-5458
(818) 760-2000
Facsimile (818) 760-3908 or by E-Mail at
Info@AGRLaw.net
Please note that any information you provide to
us via e-mail may be viewed by others and therefore, it is not a privileged
communication.
Copyright © 2006 by Abdulaziz, Grossbart & Rudman. All rights reserved.
|
 |